Wednesday, May 25, 2011

Foundation Inspection

Partial Completion of Rebar (Some 6 year old running around in the background)
Partial Completion of Rebar

Electrician Installing Floor Outlets

Partial Completion of Rebar

Completed Rebar Ready to Pour

Completed Rebar Ready to Pour

Completed Foundation Ready to Pour

5/25 Meet with Larry and Leonard.  Front porch to have 2% slope with no stoop, gas line to water feature rear porch and courtyard water feature to be on exterior master bathroom wall.
5/25 Met with Alex to inspect foundation.  Found a few places that still needed to be tied. 
5/25 Framer verified all dimensions prior to pour.
5/25 Passed Foundation and waterline test.
5/25 Concrete contractor tied up all the loose ends prior to pour.

Foundation to be poured 5/26 at 7:00 a.m.  Gas sleeve to water feature to be installed prior to pour.  

No comments:

Post a Comment