Wednesday, May 25, 2011

Foundation Inspection

Partial Completion of Rebar (Some 6 year old running around in the background)
Partial Completion of Rebar

Electrician Installing Floor Outlets

Partial Completion of Rebar

Completed Rebar Ready to Pour

Completed Rebar Ready to Pour

Completed Foundation Ready to Pour

5/25 Meet with Larry and Leonard.  Front porch to have 2% slope with no stoop, gas line to water feature rear porch and courtyard water feature to be on exterior master bathroom wall.
5/25 Met with Alex to inspect foundation.  Found a few places that still needed to be tied. 
5/25 Framer verified all dimensions prior to pour.
5/25 Passed Foundation and waterline test.
5/25 Concrete contractor tied up all the loose ends prior to pour.

Foundation to be poured 5/26 at 7:00 a.m.  Gas sleeve to water feature to be installed prior to pour.  

Sunday, May 22, 2011

Plumbing Rough and Foundation

Plumbers starting underground

Trenching sewer line

Trenching sewer line

Underground plumbing

Underground plumbing

Watering and compacting

Starting to setup rebar

Plumber and electrician are scheduled for Monday to set under slab water and electrical.  Foundation inspection scheduled for Wednesday and scheduled to pour Thursday.

Wednesday, May 4, 2011

Stem Wall Complete - Foundation Forms Started

Stew wall forms complete

Stem wall forms complete

Stem wall forms complete

Ready to pour stem walls

Pouring stem wall

Vibrating concrete stem wall

Vibrating concrete stem wall

Poured

Completed stem wall

Completed stem wall

Completed stem wall

Completed stem wall

Setting up forms for slab

Setting forms for slab


Forms for slab

Stem wall was poured Friday 4/29/11.  Rockwalls were completed 05/03/11.  Forms for the slab were started 05/04/11.  Plumber to start underground plumbing Monday 05/09/11.