Monday, February 14, 2011

Survey Stakes

Friday 2/11/11
Property survey complete, prepped to cut and fill.
Retaining wall locations placed.

Note: Monday 2/21/11 @ 1:00 p.m. Meeting scheduled with Leonard to discuss selection schedule.

Monday 2/14/11
KPM Construction scheduled to begin dirt work.
Spoke with Keven: Delay on equipment due to inclement weather at the beginning of the month.
Committed to call Tuesday with update on excavator.

Tuesday 2/15/11
Call in from Keven: Equipment to be delivered Wed 2/16 or Thursday 2/17 at the latest.
Rockwalls Scheduled to begin three days following commencement of dirt work.

No comments:

Post a Comment